The SIS&T UCPath Implementation Team is responsible for implementing mandatory student information system changes, in support of the campus conversion to the new UCPath human resources and payroll information system. Several student information systems will be impacted by the UCPath implementation because they are highly integrated into and rely upon other systems that are required to be modified by the implementation. See key dates and affected systems below:
KEY DATES
- 8:30 a.m.-1 p.m. Thursday, Sept. 6 (rescheduled from Sept. 5): Dry-run implementation test in the TEST environment only
- 9 a.m.-5 p.m. Friday, Sept. 7: Dry-run implementation test in the TEST environment only
- 9 a.m. Sunday, Sept. 16 to 5 p.m. Monday, Sept. 17: UCPath implementation cutover
- 6-11 p.m. Wednesday, Sept. 19: Post-implementation maintenance
- Thursday, Sept. 27: UCPath goes live across UCSB campus
AFFECTED SYSTEMS
A set of SIS&T-managed systems will be down from 9 a.m. Sept. 16 to 5 p.m. Sept. 17. View a calendar of all UCSB systems outages at https://www.ucpath.ucsb.edu/go-live/ucsb-system-outages. From 6-11 p.m. Sept. 19, the SIS&T will conduct UCPath maintenance, but no systems will be made completely unavailable.
FOR MORE INFORMATION
- Report issues with systems affected by UCPath: ucpath-sist@sa.ucsb.edu
- General UCSB UCPath information: https://www.ucpath.ucsb.edu
TO: SA-All, GradDiv-All, A&L-All, George Michaels, Shen Liu
CC: Suzy Danko, Aubrie Amstutz, Cindy Doherty
FROM: Keri Bradford, on behalf of Team
SENT: Monday, August 20, 2018
SUBJECT: SIS&T UCPath Implementation: General Updates
Dear Colleagues,
On behalf of the Student Information Systems & Technology (SIS&T) UCPath Implementation Team, we are writing to let you know that on Friday, September 7, our team is scheduled to conduct a dry-run test of the UCPath implementation procedures in our TEST environment only.
This means that applications which operate in our production environment will not be impacted and normal business processes will not be affected. However, SIS&T staff will have limited availability on September 7 because staff will be focused on running the test in a lead up to the UCPath cutover, scheduled for Sunday and Monday, September 16-17.
We will continue to email with occasional updates. More information about the UCPath project can be found at https://www.ucpath.ucsb.edu.
Sincerely, the SIS&T UCPath Implementation Team
James Kinneavy (Project Lead), Brian Frazier, Anthony Schmid, Keri Bradford
UCPath go-live plan as presented by project lead James Kinneavy to partners August 21.
SIS&T posted on its own Facebook and Twitter channels, and messages were shared to other channels (e.g., UCSB Staff Facebook group) and users' personal channels. Here is a sample of messages:
To: SIST-All
From: Joe Sabado
Subject: UCPath communication, implementation planning
August 24, 2018
Dear Colleagues:
As we near our portion of the UCPath implementation, I am writing to share more details with all SIS&T staff. Briefly, our involvement includes taking down several SIS&T-managed systems from 9 a.m. Sept. 16 to 5 p.m. Sept. 17, plus a smaller set of systems from 6-11 p.m. Sept. 19, in support of a larger campus implementation effort.
- More details about SIS&T's portion of the UCPath implementation can be found at http://sist.sa.ucsb.edu/projects/ucpath-implementation, including a slide deck we presented to several stakeholders earlier this week: http://sist.sa.ucsb.edu/docs/default-source/default-document-library/ucpath-go-live-plan.pdf?sfvrsn=2.
- Details about the campus conversion to UCPath can be found at https://ucsb.box.com/s/h1hifg4juvkmlnssj38jpqv225bgqrpt.
- Details about the SIS&T UCPath implementation communication plan can be found at https://ucsb.box.com/s/d7l9rmvcypa3e7iq3it6hcu1sunpuvac.
I would like to thank everyone who is contributing to this significant effort. I especially want to thank James Kinneavy, Brian Frazier, Anthony Schmid, and Keri Bradford for their coordinating efforts. If you need to contact the team, please email them at ucpath-sist@sa.ucsb.edu.
Sincerely,
Joe
Joe Sabado
Executive Director - Student Information Systems & Technology
Associate CIO of Student Affairs
University of California, Santa Barbara
Phone: 805-448-1874
Pronouns: he/him/his
TO: SA-All, GradDiv-All, George Michaels, Shen Liu
CC: Suzy Danko, Aubrie Amstutz, Cindy Doherty
FROM: sa-ucpath-sist@ucsb.edu
SENT: Thursday, August 30, 2018
SUBJECT: SIS&T UCPath: Dry-run testing and impacts Sept. 5 and Sept. 7
Dear Colleagues,
In preparation for the UCPath cutover, we are writing to let you know that from 8 a.m.-Noon on Wednesday, Sept. 5, we will be conducting a limited dry-run test, and on Friday, Sept. 7, beginning at 8 a.m., we will be conducting an end-to-end, dry-run test that is expected to last through the business day.
These tests will occur in the Test environment only and will not impact applications that operate in the Production environment. However, please note that SIS&T-managed applications listed as unavailable during the Sept. 16-17 cutover will not be available in the Test environment during the dry-run test on Friday, Sept. 7. Any non-UCPath development originally scheduled for testing or release on Friday, Sept. 7, should be rescheduled for another day. The dry-run test on Wednesday, Sept. 5, will not impact any applications in the Test environment.
While both dry-run tests are in progress, SIS&T technical staff will not be available for non-UCPath business operations. In fact, SIS&T technical staff may require specific business units to support some dry-run test operations. These units would be limited to Admissions, Office of Financial Aid & Scholarships, Office of the Registrar, and the Graduate Division. If assistance is needed from these units, they will be contacted directly by members of their own SIS&T information systems teams.
We will continue to email with occasional updates. More information can be found at http://sist.sa.ucsb.edu/projects/ucpath-implementation and https://www.ucpath.ucsb.edu.
Sincerely, the SIS&T UCPath Implementation Team
James Kinneavy (Project Lead), Brian Frazier, Anthony Schmid, Keri Bradford
TO: SA-All, GradDiv-All, George Michaels, Shen Liu
CC: Suzy Danko, Aubrie Amstutz, Cindy Doherty
FROM: sa-ucpath-sist@ucsb.edu
SENT: Wednesday, September 5, 2018
SUBJECT: SIS&T UCPath: Updates on this week's dry-run tests
Dear Colleagues,
The limited dry-run test our team had scheduled for 8 a.m.-Noon today (Sept. 5) could not be completed, due to an unrelated network connectivity issue. Instead, it has been rescheduled for 8 a.m.-Noon tomorrow, Sept. 6. This test will occur in the Test environment only and will not impact applications that operate in the Production environment.
Please remember that, beginning at 8 a.m. Friday, Sept. 7, we will be conducting a second dry-run test that is expected to last through the business day. During Friday's end-to-end test, which will occur in the Test environment, the SIS&T-managed applications listed as unavailable during the Sept. 16-17 cutover will not be available in the Test environment. See a full list of affected applications at https://www.ucpath.ucsb.edu/go-live/ucsb-system-outages.
Any non-UCPath development originally scheduled for testing or release on Friday, Sept. 7, should be rescheduled for another day. While both dry-run tests are in progress, SIS&T technical staff will not be available for non-UCPath business operations.
SIS&T technical staff may require specific business units to support some dry-run test operations. These units would be limited to Admissions, Office of Financial Aid & Scholarships, Office of the Registrar, and the Graduate Division. If assistance is needed from these units, they will be contacted directly by members of their own SIS&T information systems teams.
We will continue to email with occasional updates. More information can be found at http://sist.sa.ucsb.edu/projects/ucpath-implementation and https://www.ucpath.ucsb.edu.
Sincerely, the SIS&T UCPath Implementation Team
James Kinneavy (Project Lead), Brian Frazier, Anthony Schmid, Keri Bradford
TO: SA-All, GradDiv-All, George Michaels, Shen Liu
CC: Suzy Danko, Aubrie Amstutz, Cindy Doherty
FROM: sa-ucpath-sist@ucsb.edu
SENT: Monday, September 10, 2018
SUBJECT: SIS&T UCPath: We are ready for cutover on Sunday
Dear Colleagues,
We are happy to report that the UCPath dry-run tests our team conducted last Thursday and Friday were successful and that we are all-systems-go for the full-scale cutover of UCPath on Sunday and Monday, Sept. 16-17. It took a team of 20 and much hard work to plan and practice the steps required for executing a project of this size, and now we have a high degree of confidence for success on Sunday.
Please review the full list of systems that will be unavailable during the cutover, scheduled to begin at9 a.m. Sunday, at https://www.ucpath.ucsb.edu/
Once cutover activities have been completed and all SIS&T-managed systems are fully restored, you will receive an email from our team. If you experience any problems after restoration, please report any issues to support@sa.ucsb.edu.
Our team will continue with plans for UCPath maintenance from 6-11 p.m. next Wednesday, Sept. 19, however, we discovered during last week's dry-run tests that we could conduct all necessary maintenance without taking down any systems. It is possible that users will notice brief periods of disruption during maintenance, but no systems will be completely unavailable that evening.
We will continue to email with occasional updates. More information can be found at http://sist.sa.ucsb.edu/
Sincerely, the SIS&T UCPath Implementation Team
James Kinneavy (Project Lead), Brian Frazier, Anthony Schmid, Keri Bradford
SIS&T posted on its own Facebook and Twitter channels, and messages were shared to other channels (e.g., UCSB Staff Facebook group) and users' personal channels. Here is a sample of messages:
TO: abog@lsmail.ucsb.edu, ucsbadvs@ltsc.ucsb.edu, GDAll@graddiv.ucsb.edu, SAALL@sa.ucsb.edu, george_michaels@ucsb.edu, shenliu@ucsb.edu, kam.choi@ucsb.edu, emccurdy@ucsb.edu
CC: suzy@ucsb.edu, aubrie@ucsb.edu, cdoherty@ucsb.edu, joesabado@ucsb.edu, kinneavy-j@ucsb.edu, frazier@ucsb.edu
FROM: Keri Bradford, on behalf of Team
CHANNEL(S): ucpath-sist@sa.ucsb.edu
SENT: 6:03 p.m. Sunday, September 16, 2018
SUBJECT: UCPath: SIS&T-managed systems restored; 9/19/18 maintenance scheduled
Dear Colleagues:
We are writing to let you know that all SIS&T-managed systems made unavailable by the UCPath implementation are now fully restored. Other campus systems may still be affected. For a complete list of all systems outages, please visit https://www.ucpath.ucsb.edu/go-live/ucsb-system-outages.
From 6-11 p.m. Wednesday, September 19, our team will be conducting UCPath maintenance, but we no longer need to take down any systems to do so. It is possible that users could notice brief periods of disruption during maintenance, but no systems will be completely unavailable that evening.
If you experience any issues with SIS&T-managed systems, please report them to ucpath-sist@sa.ucsb.edu.
Sincerely, the SIS&T UCPath Implementation Team